Decision details

PROPOSED AMENDMENTS TO TRAFFIC REGULATION ORDERS FOR THE WOKING TRANSPORT INFRASTRUCTURE PACKAGE (EXECUTIVE FUNCTION)

Decision Maker: Woking Joint Committee

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decision:

Woking Joint Committee agreed to:

 

(i)    Note the results of the advertising of the TRO’s and the update from the previous March 2017 report.

(ii)   Authorise the advertising of the Traffic Regulation Order for the creation of a 30mph speed limit along Victoria Way between the junction with Church Street West (the start of the existing southbound 30mph speed limit) to Chertsey Road, to include revoking of the existing speed limit of 40mph (NB – Step 6 of the SCC Speed Limit Policy states that if the Committee disagree with with recommendations presented to them by the Highways Manager and wish to proceed with an alternative option, then the issue must be submitted for decision by the Cabinet Member responsible for road safety).

(iii)  Authorise the Surrey County Council Area Highways Manager, in consultation with the Woking Town Centre Project Manager and the Chairman and Vice Chairman, to advertise the appropriate legal notices in accordance with the Road Traffic Regulation Act 1984, the effect of which will be to implement the proposed changes and revoke any existing traffic orders, as necessary;

(iv) Agree that the Surrey County Council Area Highways Manager, in consultation with the Woking Town Centre Project Manager and the Chairman and Vice Chairman, resolve any objections received in connection with the proposals, and implement subject to no irresolvable objections.

 

Reasons:

 

The amendments to the TRO are sought as part of the package of improved transport and access facilities to the town centre as well as the provision of a high quality urban environment as part of the major public realm improvements to Woking Town Centre.

 

 

Publication date: 28/06/2017

Date of decision: 28/06/2017

Decided at meeting: 28/06/2017 - Woking Joint Committee

Effective from: 05/07/2017