HIGHWAYS FORWARD PROGRAMME [EXECUTIVE FUNCTION FOR DECISION]

Decision Maker: Reigate and Banstead Local Committee

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The Local Committee (Reigate & Banstead) agreed to:

General

(i)       Note that the Reigate and Banstead Local Committee’s devolved highways budget for capital works within the Medium Term Financial Plan 2017-20 is £36,363 in 2018/19 and 2019/20 and that the revenue budget for 2018/19 is £40,910.

(ii)      Authorise delegation of authority to the Area Highway Manager, in consultation with the Local Committee Chairman and Vice-Chairman, to agree a revised programme of highway works for 2018/19 if there is a change in the Local Committee’s devolved budget;

(iii)   Note that should there be any changes to the programme of highway works as set out in this report, a report will be taken to a future meeting of Reigate &Banstead Local Committee to inform members of the changes.

And resolved to:

Capital Improvement Schemes (ITS)

(iv)    Agree that the capital improvement schemes allocation for Reigate and Banstead be used to progress the Integrated Transport Schemes programme set out in Annex 1;

(v)     Authorise that the Area Highway Manager, in consultation with the Local Committee Chairman and Vice-Chairman, be able to vire money between the schemes agreed in Annex 1, if required;

(vi)    Agree that the Local Committee Chairman, Vice-Chairman and Area Highway Manager, together with the relevant local divisional Member are able to progress any scheme from the Integrated Transport Schemes programme, including consultation and statutory advertisement that may be required under the Road Traffic Regulation Act 1984, for completion of those schemes.  Where it is agreed that a scheme will not be progressed, this will be reported back to the next formal meeting of the Local Committee for approval.

Revenue Maintenance

(vii)Authorise the Area Maintenance Engineer, in consultation with the Local Committee Chairman, Vice-Chairman and relevant local divisional Member, to use £40,910 of the revenue maintenance budget for 2018/19 as detailed in Table 2 of this report;

And agreed:

(viii)  The Area Maintenance Engineer, in consultation with the Local Committee Chairman and Vice-Chairman, be able to vire the revenue maintenance budget between the identified work headings in Table 2;

And resolved to:

(ix)    Agree that the revenue maintenance gang be managed by the Area Maintenance Engineer on behalf of Member

 

REASONS FOR RECOMMENDATIONS:

To agree a forward programme of highways works in Reigate and Banstead for 2018/19 – 2019/20, funded from the Local Committee’s devolved budget. 

 

 

 

Publication date: 07/12/2017

Date of decision: 04/12/2017

Decided at meeting: 04/12/2017 - Reigate and Banstead Local Committee