That the Local Committee [Elmbridge] agreed:

 

(i)    To prioritise St Mary’s Road, Surbiton, for resurfacing in 2018-19, using the £38,636 that was allocated for a maintenance scheme by Committee in September 2017 from the 2018-19 capital budget;

(ii)   To authorise the advertisement of a traffic regulation order to permit buses, delivery vehicles and emergency services’ vehicles to pass through a “gateway” that has been included in the detailed design for the next phase of the Burwood Road junction with Pleasant Place scheme, to provide a turning opportunity for these vehicles;

(iii)  To approve seven new ITS projects, as set out in the report, to be funded from the parking surplus allocations that are not yet fully committed;

(iv)  To approve the advertisement of a traffic regulation order for a new U-turn ban in Hampton Court Way between Embercourt Road and the Ember River bridge, in both directions, and that if there are no significant objections to the traffic regulation order, that the order is made to enable the new ban to come into force as soon as possible;

(v)   To approve nineteen new bus stop clearways as detailed in paragraphs 2.9.1 to 2.9.4 and Annexes G and H of the report;

(vi)  To authorise the Area Highway Manager in consultation with the Chairman, Vice Chairman, and relevant Divisional Member(s) to undertake all necessary procedures to deliver the agreed programmes.

 

Reasons: Recommendations are made to enable the 2018-19 Highways programmes funded by the Local Committee to be decided in good time to facilitate timely delivery of those programmes.

 

Further recommendations have been made, to facilitate implementation of the next phase of the Burwood Road junction with Pleasant Place UTS scheme, to enable a new U-turn ban to be introduced to mitigate a pattern of casualties, and to facilitate the introduction of a number of bus stop clearways.

 

Publication date: 06/12/2017

Date of decision: 04/12/2017

Decided at meeting: 04/12/2017 - Elmbridge Local Committee

Effective from: 14/12/2017