HIGHWAYS UPDATE [EXECUTIVE ITEM - FOR DECISION]

Decision Maker: Elmbridge Local Committee

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decision:

That the Local Committee (Elmbridge) agreed:

 

(i)     To authorise the creation of a new cycle route along the east side of Seven Hills Road, in the form of a shared surface on the existing (widened) footway, in consultation with the Divisional Members and residents as appropriate;

 

(ii)   To authorise the Area Highway Manager to finalise the preferred options for improving the junctions at either end of Baker Street, Weybridge, in consultation with the Divisional Member and local community as appropriate, and to undertake any necessary legal procedure that may be necessary to deliver this scheme;

 

(iii)  To authorise the creation of a new cycle route connecting the end of Grotto Road to Oatlands Drive, in the form of a shared surface on the existing (widened) footpath, in consultation with the Divisional Members and residents as appropriate;

 

(iv)  To authorise the Area Highway Manager to advertise the legal notice for the introduction of a new Pegasus Crossing in Copsem Lane, Esher, at the point where the track underneath the powerlines crosses the road, in consultation with the Divisional Member and local stakeholders as appropriate, and to resolve any representations that might be received;

 

(v)   Subject to Elmbridge Borough Council awarding CIL funding, to authorise the Area Highway Manager to advertise the legal notice for the removal of one Zebra Crossing and the introduction of a new Zebra Crossing in Walton High Street , in consultation with the Divisional Member, ward members and local community as appropriate, and to resolve any representations that might be received;

 

(vi)  Subject to Elmbridge Borough Council awarding CIL funding, authorise the Area Highway Manager to deliver the road safety scheme Ember Lane, including any necessary legal procedure, in consultation with the Divisional Member and local community as appropriate ;

 

(vii)[Recommendation deleted as CIL decision has been deferred a decision pending consideration of whether the proposed scheme is the most appropriate] To reinstate the Task Group to consider the way forward;

 

(viii)Delegate authority to the Area Highway Manager to develop an overnight weight restriction for Oxshott Village, taking into account any potential impact on surrounding roads, in consultation with Divisional and Ward Members, the Mole Valley Local Committee and local communities as appropriate, including any legal procedure necessary to introduce the restriction, and should a scheme be identified that is supported by these stakeholders to implement the scheme;

 

(ix)  Agree the 2021-22 programme of Capital Maintenance schemes, as detailed in Table 2 below, and to authorise the Area Team Manager, in consultation with the Chairman, Vice Chairman and Divisional Member to amend this programme as appropriate should unforeseen circumstances arise that would put the programme at risk of delivery;

 

(x)   Agree to remove from the programme of works the part-time pedestrianisation proposal for Bridge Road, East Molesey, which emerged from the Active Travel scheme;

 

(xi)  Agree to defer the trial of a new part time pedestrian area at the Lime Tree in Thames Ditton High Street, and to delegate authority to the Area Highway Manager to continue discussion with the Division and Ward Members and the local community with the intent of agreeing a consensus on how Thames Ditton High Street might be improved;

 

(xii)Authorise the Area Highway Manager in consultation with the Chairman, Vice Chairman, and relevant Divisional Member(s) to undertake all necessary procedures to deliver the agreed programmes.

 

Reasons:

 

Elmbridge Borough Council has awarded CIL funding for implementation of a number of schemes that have been promoted by the Local Committee.  At the time of writing this report the outcomes of some applications for CIL funding were not known.  Delegated authority is needed to facilitate the delivery of these schemes in consultation with local stakeholders.

 

The feasibility study for speed and traffic management measures in Oxshott Village centre has begun.  A proposed overnight weight restriction has been identified as a potential quick win; delegated authority is needed to move this forward through its consultative and legal processes.

 

A programme of capital maintenance schemes needs to be agreed to invest Committee’s £311,000 allocation for this purpose.  Officers have worked with Members to agree priorities.  However should unforeseen circumstances arise that might put the programme at risk, the Area Highway Manager needs flexibility to amend the programme as appropriate.

 

In March 2021 Committee agreed to two public consultations – relating to Bridge Road in East Molesey and Thames Ditton High Street – these consultations have now been completed in consultation with local Divisional and Ward Members.

 

Publication date: 16/07/2021

Date of decision: 14/07/2021

Decided at meeting: 14/07/2021 - Elmbridge Local Committee

Effective from: 24/07/2021

Accompanying Documents: