Agenda item

TRAVEL SMART - LOCAL SUSTAINABLE TRANSPORT FUND

[Paul Fishwick]

(Approximate starting time – 8.40)

 

To approve the draft programme for 2013/14, and delegate authority to the Chairman of the LSTF Delivery Board to approve amendments to the LSTF programme to enable full spend if any savings are found within the current grant funded budget.

Decision:

The Local Committee (Woking):

 

          i.          Agreed the draft programme of LSTF (Key Component and Large Bid) allocation for schemes for the 2013/14 financial year as set out in Annex A.

 

         ii.         Delegated amendments to the LSTF Programme to the Chairman of the LSTF Delivery Board in consultation with the Local Committee Chairman and appropriate county and borough officers and members. 

 

        iii.        Agreed to consider the responses from the Egley Road survey at the forthcoming Task Group meeting on 31 January 2013 and report back to this Committee at the next planned meeting.

 

        iv.        Agreed to carry out a feasibility study for the A245 Parvis Road (Camphill Road to Chertsey Road) Phase 2 (junction treatments) and report back to this Local Committee at the next planned meeting.

 

Reason:

To enable Travel SMART schemes in Woking to be progressed.

Minutes:

Paul Fishwick introduced the item which set out the draft programme for 2013/14. Paul referred to the petition on the Chobham Road crossing presented earlier on in the agenda and confirmed that he would liaise with the petitioner over the consultation on this item.

 

Mrs Smith suggested the the Bisley to Knaphill cycle route could follow Warbury Lane and Barrs Lane.  Paul agreed to look at this as an additional possibility, but the other route was required for the link to Knaphill.

 

In response to Cllr Wilson, Paul confirmed that he had written approval from the Highways Agency that they were happy with the proposals for the bridge over the motorway on the A245 raised in the safety audit.

 

It was confirmed that the community funding was agreed in the original bid, and this would continue to be focussed on Sheerwater and Maybury.

 

RESOLVED

The Local Committee (Woking):

 

          i.          Agreed the draft programme of LSTF (Key Component and Large Bid) allocation for schemes for the 2013/14 financial year as set out in Annex A.

 

         ii.         Delegated amendments to the LSTF Programme to the Chairman of the LSTF Delivery Board in consultation with the Local Committee Chairman and appropriate county and borough officers and members. 

 

        iii.        Agreed to consider the responses from the Egley Road survey at the forthcoming Task Group meeting on 31 January 2013 and report back to this Committee at the next planned meeting.

 

        iv.        Agreed to carry out a feasibility study for the A245 Parvis Road (Camphill Road to Chertsey Road) Phase 2 (junction treatments) and report back to this Local Committee at the next planned meeting.

 

 