20/03/2023 - Your Fund Surrey Application - CF171 Leatherhead & Dorking Gymnastics ref: 5257    Recommendations Approved

This decision record sets out the key information for publication on the decision by the Executive Director for Customer and Communities and the Deputy Chief Executive & Executive Director of Resources, in consultation with the Cabinet

Member for Communities & Community Safety and the Cabinet Member for Finance & Resources, to approve an additional 10% contingency payment due to inflation hardship for a Your Fund Surrey (YFS) project located in Woking. The agreed recommendations are set out below on the face of this decision record.

Decision Maker: Deputy Chief Executive and Executive Director for Resources

Decision published: 22/03/2023

Effective from: 20/03/2023

Decision:

 

It was AGREED:

 

1.               to fund up to an additional 10% of the original funded value (up to £50,000) for increased costs relating to current inflation levels towards Your Fund Surrey project CF171 Leatherhead & Dorking Gymnastics.

 

a.    The original grant award for £500,000 was granted 05/07/2022. An additional 10% inflation hardship claim of up to £50,000 is allowable, and fully in line with, the Cabinet decision from November 20221.

b.    Works are currently underway and approaching fit-out of the new building.

c.     Costs have increased due to increased material and labour costs across the build, including construction, electrics and plumbing. The evidence provided by the applicant sufficiently demonstrates the impact of inflationary pressures on the project.

d.    Contingency funding included within the original grant award (£63,000) is also being claimed towards increased costs, however the additional 10% is also required to ensure successful completion of the build and achievement of the assessed community benefits.

 

The remaining build costs are £116,406 The project cost changes are detailed below:

CF171 Leatherhead & Dorking Gymnastics Cost Breakdown

2020 quote

Jan-23

Uplift

Reason for change

Steel work

£103,840

£45,690

Price increase at 40%

Roof covering

£67,500

£22,275

Price increase at 30%

Cladding

£48,250

£15,923

Price increase at 30%

Shutters & fire doors

£19,500

£5,363

Price increase at 25%

Mechanical & Electrical

£83,950

£23,086

Price increase across the board at 25%

Additional works required to reception area

£0

£4,069

Structural issue

Total additional cost

£116,406

 

 

Total grant award including contingency

£500,000

 

Grant paid to date

£481,798

 

Grant balance

£18,202

 

 

Outstanding balance to be funded:

 

£116,406

 

 

Balance of YFS grant funding

£18,202

 

 

10% extra YFS inflation hardship contingency

£50,000

 

 

 

Balance to be funded by applicant

£48,204

 

 

 

 

Lead officer: Anna D'Alessandro


09/03/2023 - Facilities Management Consultancy Services Contract ref: 5255    Recommendations Approved

A Procurement Report was previously approved for the award of Facilities Management Consultancy Services for Gardiner & Theobald LLP. Further approval is required for additional consultancy work to be undertaken under the contract to the value of £53,166 which increases the total contract value to £545,946.

Decision Maker: Deputy Chief Executive and Executive Director for Resources

Decision published: 09/03/2023

Effective from: 09/03/2023

Decision:

It was AGREED that:

 

1.           The contract with Gardiner & Theobald LLP can be increased in value to cover the additional services as detailed above.