Decision details

HIGHWAYS UPDATE (EXECUTIVE FUNCTION)

Decision Maker: Woking Joint Committee

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decision:

The Woking Joint Committee:

 

(i)     Noted the progress with ITS highways and developer funded schemes and revenue funded works for the 2016/17 financial year and requested that Bateson Way be re-instated on the programme.

(ii)    Noted the budgetary position.

(iii)  Noted that a further Highways Update will be brought to the next meeting of this Committee.

REASONS:

 

The above recommendations are made to enable progression of all highway related

schemes and works. It was noted that Bateson Way was not part of the Sheerwater Regeneration so should be re-instated on the programme.

 

Publication date: 21/09/2016

Date of decision: 21/09/2016

Decided at meeting: 21/09/2016 - Woking Joint Committee