Decision details

ROAD SAFETY OUTSIDE SCHOOLS ST JOSEPH'S SCHOOL, ROSEBANK, EPSOM [EXECUTIVE FUNCTION - FOR DECISION]

Decision Maker: Epsom and Ewell Local Committee

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decision:

That the Local Committee [Epsom & Ewell] agreed:

 

(i)        To allocate funding to begin a feasibility study for St Joseph’s School this Financial Year 2019-20 at a maximum initial cost of £5,000, to include consideration of measures in both Rosebank and Whitehorse Drive, subject to the identification of suitable funding from the deferment of a project already scheduled for this year.

(ii)        [on a vote 8 votes FOR to 1 AGAINST] To ask the parking engineer to draw up proposals for the relaxation of parking for a limited time period, at the start and end of the school day, on parts of the Abelea Green estate, to allow an additional park and stride location, for inclusion in the parking review to be considered at the September 2019 meeting of the Committee.

 

Reasons:  To consider engineering improvements in Rosebank and Whitehorse Drive that may be beneficial and the option for an additional park and stride location.

Publication date: 28/06/2019

Date of decision: 24/06/2019

Decided at meeting: 24/06/2019 - Epsom and Ewell Local Committee

Effective from: 27/06/2019

Accompanying Documents: