Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
The Local Committee (Reigate & Banstead) agreed:
i)
To note the contents of this report.
ii)
To note the increased capital budget for 2020/21, following the
full council meeting held in December 2019, from £211,111
which was reported at the December Local Committee to
£334,000.
iii)
That the capital improvement schemes allocation for Reigate and
Banstead in 2020/21 be used to progress the Integrated Transport
Schemes programme as set out in Annex 4.
iv) To note the increased capital maintenance budget for 2020/21 from £174,000 to £295,000, following the full council meeting held in December 2019. Which will be used to fund capital maintenance schemes, divided equitably between divisional members. Schemes to be progressed using this funding will be agreed by the Reigate & Banstead Maintenance Engineer in consultation with the Local Committee Chairman, Vice-Chairman and divisional members.
Reason for decisions:
The above decisions were made to update the Local Committee on the outcome of the 2019/20 highway works programme in Reigate and Banstead, and amendments to the 2020/21 Local Committee capital budget.
Publication date: 03/03/2020
Date of decision: 02/03/2020
Decided at meeting: 02/03/2020 - Reigate and Banstead Local Committee
Effective from: 10/03/2020
Accompanying Documents: