Manby Lodge Infant School expansion

Decision Maker: Cabinet Member for Schools and Learning Decisions

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

To decide on the proposal to expand Manby Lodge Infant School from 2 to 3 forms of entry, increasing the total capacity of the school from 180 to 270 pupils

Decision:

In order to meet increased demand for primary school places in Weybridge, it was agreed that:

 

·         Manby Lodge Infant School be enlarged by 1 form of entry (from 2 FE to 3 FE) on 1 September 2015.

·         The school roll be increased by one form each year until September 2017 when its capacity will be 270 pupils.

·         An associated building programme go ahead, in a single phase, to provide appropriate new classrooms and facilitate the removal of all temporary accommodation on site. The new build will improve the overall layout of the school and is intended to provide a modern educational facility which will enhance learning.

Report author: Melanie Harris

Publication date: 14/05/2014

Date of decision: 14/05/2014

Decided at meeting: 14/05/2014 - Cabinet Member for Schools and Learning Decisions