Decision Maker: Cabinet
Decision status: Recommendations approved
Is Key decision?: Yes
Is subject to call in?: Yes
Following Cabinet’s approval to convert the Council’s street lights to LED in October 2018, Officers have carried out the necessary work to agree the legal and commercial aspects of the Change Agreement and are now ready to proceed to the execution of the Deed of Variation to the PFI Contract.
RESOLVED:
Reason for Decisions:
Energy price inflation was increasing at a significant rate (5%-14% per annum) and to ensure lights were operational when needed, there was little opportunity for the Council to control or reduce its energy costs.
LED technology in street lighting had matured significantly in recent years while the costs had reduced. Many Highway Authorities had either embarked on an LED conversion programme or were in the process of planning to commence one within the next 2-3 years.
Converting to LED would reduce energy consumption by 60% delivering £2 million per year energy savings at today’s prices as well as reducing carbon impact by 6200 tonnes.
In addition to converting to LED street lighting and upgrading the Central Management System, officers would be able to explore additional innovations now being used or being developed for use with street lighting such as:
· Providing real-time traffic movement data to help understand and ease congestion
· Adjust lighting levels of traffic routes to suit actual traffic levels which would lead to additional energy savings
· Environmental sensors to detect and monitor air quality
The potential for these innovations may be in direct relation to street lighting (e.g. dimming in response to traffic levels) or in providing a communications network for other areas of the Council (and extending to partners in District and Borough Councils) to connect equipment to improve the services and outcomes they deliver.
Furthermore, these innovations may present grant funding opportunities through central Government departments and the Local Enterprise Partnerships (LEPs) which would reduce the borrowing requirement for the Council.
The PFI contract allowed for changes to the specification and service. Following Cabinet approval in January 2018, a Change Notice had been issued under the contract and subject to this approval, officers will finalise the contractual documents and execute a Deed of Variation.
[The decisions on this item can be called in by the Environment Select Committee]
Report author: Paul Wheadon
Publication date: 31/10/2018
Date of decision: 30/10/2018
Decided at meeting: 30/10/2018 - Cabinet
Effective from: 08/11/2018