Decision:

the Cabinet Member approved:

 

a)         The proposed prioritisation process set out in Annex A of the report;

 

b)         The proposed ITS schemes to be funded from the planned 2025/26 Countywide Integrated Transport Scheme budget set out in the revised Annex B of the report (attached); and

 

c)         To delegate authority to the Highways Engagement and Commissioning Manager to make any minor amendments to the schemes which may be required to ensure that the schemes are progressed, in consultation with the relevant Divisional Member and, where required, the Cabinet Member.

Publication date: 30/09/2024

Date of decision: 24/09/2024

Decided at meeting: 24/09/2024 - Cabinet Member for Highways, Transport and Economic Growth Decisions

Effective from: 02/10/2024

Accompanying Documents: