To report progress made with the delivery of proposed highways schemes, developer funded schemes, and revenue funded works for the 2014/15 financial year.

 

The report also provides an update on the latest budgetary position for highway schemes, revenue maintenance and Community Enhancement expenditure.

 

Decision:

The Local Committee (Surrey Heath) agreed to:

 

(i)     Note the progress with the ITS highways and developer funded schemes, and revenue funded works for the 2014/15 financial year.           

(ii)    Note the budgetary position.

(iii)  Agree the proposed capital works programme for 2015/16.  

(iv)  Note that a further Highways Update will be brought to the next meeting of this Committee.

 

Minutes:

The Committee received a report on the progress made with the delivery of proposed highways schemes, developer funded schemes, and revenue funded works for the 2014/15 financial year.  The report also provided an update on the latest budgetary position for highway schemes, revenue maintenance and Community Enhancement expenditure.

 

It was noted that 13 of the 16 contingency schemes had already been delivered.  Some of the schemes included on table 5 of the report were believed to also be in the Operation Horizon long term programme and the Highways Manager agreed to clarify this outside the meeting.  The Highways Team were commended for their work on the programme and also with keeping ditches and drainage clear so that Surrey Heath avoided flooding issues.

 

The Local Committee (Surrey Heath) agreed to:

 

(i)     Note the progress with the ITS highways and developer funded schemes, and revenue funded works for the 2014/15 financial year.           

(ii)    Note the budgetary position.

(iii)  The proposed capital works programme for 2015/16.

(iv)  Note that a further Highways Update will be brought to the next meeting of this Committee.