MAJOR PROJECTS UPDATE REPORT

Meeting: 12/03/2015 - Surrey Heath Local Committee (Item 13)

13 MAJOR PROJECTS UPDATE REPORT - Steve Howard pdf icon PDF 178 KB

The report is to update members on the current status and feedback from the EM3 LEP for the Surrey Heath Major transport schemes, namely the A30 / A331 Meadows Gyratory and Corridor Improvements, and Blackwater Valley Better Connectivity Sustainable Transport Package.

 

 

Additional documents:

Decision:

The A30 / A331 Meadows Gyratory and Corridor Improvements scheme is currently programmed to commence works in the 2015/16 financial year, but the Blackwater Valley Better Connectivity STP only has grant funding available for 2015/16 financial year. Therefore, this project will need to be completed by 31 March 2016.

 

The Local Committee (Surrey Heath) agreed to:

(i)     Note the progress made so far with the Major schemes submission (Annexes 1 & 2 provides layout plans).

(ii)    Note the draft proposals for the A30 / A331 Meadows Gyratory, and the Blackwater Better Connectivity STP - phase 1 (Annex 3).

(iii)  Consultation on the A30/A331 The Meadows project and the A331 junction with Riverside Way (Blackwater Valley STP) during the period 15 June to 26 July (6 weeks), and to delegate authority to the Area Team Manager, in consultation with the Chairman, Vice Chairman, the Member Task Group for Major Schemes, and the Project Managers for both projects to agree the final consultation material.

 

Minutes:

The A30 / A331 Meadows Gyratory and Corridor Improvements scheme is currently programmed to commence works in the 2015/16 financial year, but the Blackwater Valley Better Connectivity STP only has grant funding available for 2015/16 financial year. Therefore, this project will need to be completed by 31 March 2016.

 

Steve Howard and his team were thanked for their hard work on this project and for taking forward the funding bids.  Members noted that they would like to see a “cycling strategy” for Surrey Heath and suggested the new cycling officer be invited along to an informal meeting.

 

The Local Committee (Surrey Heath) agreed to:

(i)     Note the progress made so far with the Major schemes submission (Annexes 1 & 2 provides layout plans).

(ii)    Note the draft proposals for the A30 / A331 Meadows Gyratory, and the Blackwater Better Connectivity STP - phase 1 (Annex 3).

(iii)  Consultation on the A30/A331 The Meadows project and the A331 junction with Riverside Way (Blackwater Valley STP) during the period 15 June to 26 July (6 weeks), and to delegate authority to the Area Team Manager, in consultation with the Chairman, Vice Chairman, the Member Task Group for Major Schemes, and the Project Managers for both projects to agree the final consultation material.