32 HIGHWAYS UPDATE AND FORWARD PLAN 2014 / 2015 pdf icon PDF 85 KB

To report progress made with the delivery of proposed highways schemes, developer funded schemes, and revenue funded works for the 2013/14 financial year.

 

To provide an update on the latest budgetary position for highway schemes, revenue maintenance and Community Enhancement expenditure.

 

To agree the 2014/15 programme of capital maintenance and ITS schemes

 

Decision:

The Local Committee received a report on progress made with the delivery of proposed highways schemes, developer funded schemes, and revenue funded works for the 2013/14 financial year.  The report provided an update on the latest budgetary position for highway schemes, revenue maintenance and Community Enhancement expenditure, and proposed a plan for the 2014/15 programme of capital maintenance and ITS schemes.  The proposed plan for 2014/15 allocates the majority of funding towards the Toshiba / Frimley roundabout improvement scheme, which was agreed unanimously.

 

The Local Committee (Surrey Heath) agreed to:

 

(i)    Note the progress with the ITS highways and developer funded schemes, and revenue funded works for the 2013/14 financial year,          

(ii)   Note the progress with budget expenditure,  

(iii)  Note that a further Highways Update will be brought to the next meeting of this Committee,

(iv)Agree the capital scheme and contingency plan proposals for 2014/15 (subject to a further informal meeting to ensure contingency priorities are still current) as shown in section 2.5 subject to the anticipated provision of capital budget.

 

Minutes:

The Local Committee received a report on progress made with the delivery of proposed highways schemes, developer funded schemes, and revenue funded works for the 2013/14 financial year.  The report provided an update on the latest budgetary position for highway schemes, revenue maintenance and Community Enhancement expenditure, and proposed a plan for the 2014/15 programme of capital maintenance and ITS schemes. 

 

The proposed plan for 2014/15 allocates the majority of funding towards the Toshiba / Frimley roundabout improvement scheme, which was agreed unanimously.  If this scheme did not however go ahead, a proposed alternative list was discussed.  The list would be supplementary to Highways works under Operation Horizon and included schemes recommended by engineers.  Members agreed to look at this list and discuss the agreement of the schemes at a later date.

 

Members also discussed the expenditure on signage in the Borough.  Traffic signs are subject to strict regulations and any change on these is subject to written permission from the Department of Transport. 

 

An update was also given on the Red Road.  Roundabouts may not be viable, so consultation is taking place with the Police regarding the introduction of average speed cameras.  Figures show there have been no accidents reported since May 2013 and will continue to be monitored.

 

The Local Committee (Surrey Heath) agreed to:

 

(i)    Note the progress with the ITS highways and developer funded schemes, and revenue funded works for the 2013/14 financial year,          

(ii)   Note the progress with budget expenditure,  

(iii)  Note that a further Highways Update will be brought to the next meeting of this Committee,

(iv)Agree the capital scheme and contingency plan proposals for 2014/15 (subject to a further informal meeting to ensure contingency priorities are still current) as shown in section 2.5 subject to the anticipated provision of capital budget.