OPERATION HORIZON

Meeting: 13/03/2014 - Surrey Heath Local Committee (Item 44)

44 OPERATION HORIZON pdf icon PDF 41 KB

The report records the progress made in the first year of the 5-year carriageway investment maintenance programme, any changes to the year one programme and the success of the countywide Operation Horizon project to date. Progress of the supporting surface treatment programme of roads in Surrey Heath that have been carried out this financial year is also reported.

 

It sets out the proposed Operation Horizon roads within Surrey Heath for the year two programme (financial year 2014/15), along with the remaining approved roads to be completed in years three to five (2015 – 2018).

 

Additional documents:

Decision:

The Committee received a report which recorded the progress made in the first year of the 5-year carriageway investment maintenance programme, any changes to the year one programme and the success of the countywide Operation Horizon project to date. Progress of the supporting surface treatment programme of roads in Surrey Heath that have been carried out this financial year were also reported.

 

The report also set out the proposed Operation Horizon roads within Surrey Heath for the year two programme (financial year 2014/15), along with the remaining approved roads to be completed in years three to five (2015 – 2018).

 

The Local Committee (Surrey Heath) noted:

 

a)    The success of the countywide 5-year programme in year one.

b)    The progress of Operation Horizon roads, Surface Treatment  roads, and changes in year one in Surrey Heath in Annex 1.

c)    The proposed programme of Operation Horizon roads for Surrey Heath for year two (2014/15) and the remaining approved roads to be undertaken in years three to five (2015-2018) listed in Annex 1.

Minutes:

The Committee received a report which recorded the progress made in the first year of the 5-year carriageway investment maintenance programme, any changes to the year one programme and the success of the countywide Operation Horizon project to date. Progress of the supporting surface treatment programme of roads in Surrey Heath that have been carried out this financial year were also reported.

 

The report also set out the proposed Operation Horizon roads within Surrey Heath for the year two programme (financial year 2014/15), along with the remaining approved roads to be completed in years three to five (2015 – 2018).

 

It was noted that bids were being made for additional Government funding to tackle flood damaged roads.  Councillors were concerned that some roads had deteriorated in the recent bad weather and that priorities needed to be regularly reviewed.

 

The Local Committee (Surrey Heath) noted:

 

a)    The success of the countywide 5-year programme in year one.

b)    The progress of Operation Horizon roads, Surface Treatment  roads, and changes in year one in Surrey Heath in Annex 1.

c)    The proposed programme of Operation Horizon roads for Surrey Heath for year two (2014/15) and the remaining approved roads to be undertaken in years three to five (2015-2018) listed in Annex 1.