An update
sheet was tabled at the meeting and is attached as Annex 2 to the
minutes.
Officers:
Caroline Smith,
Planning Development
Manager
Stephen
Jenkins, Deputy Planning Development Manager
Nancy
El-Shatoury, Principal Lawyer
Mike
Burch, Senior Flood Risk and Network Resilience Officer
Richard
Thomas, Peter Brett Associates
Speakers:
Mr
John Douglass, made representations in objection to the
application. The following key points were
made:
·
Chartered electrical engineer and a representative
from the Shepperton against Watersplash
Group.
·
EA originally objected to the application on various
grounds and as a result Cemex withdrew
and amended the application.
·
EA originally objected to proposals on flood risk
grounds but following discussions with applicant the EA withdrew
objections but planning officers failed to tell you why objections
were with withdrawn. These were withdrawn because ground water
flooding was not within the remit of the EA anymore and was now a
responsibility of the lead flooding authority, Surrey County
Council.
·
Anomalies in the planning officers report with
serious consequences for water supply at Fordbridge Park.
Mr
John Fennell, made representations in objection to the
application. The following key points were
made:
·
Explained that he was an engineer.
·
Planning officers conclusions mask flaws of a
catastrophic flooding event in Shepperton.
·
Experts consultants used by the council have applied
old government guidelines to predict flood events to approximately
1 in 30,000 years. Despite the site being in a EA flood zone 3A. We
believe that a flood event could occur approximately 1 in 20 years
using the most updated guidelines from government.
·
Believe there is a chance that low lying
Shepperton could be flooded, which is
5ft below Watersplash farm.
Mr
Derek Langridge, made representations in objection to the
application. The following key points were
made:
·
Manager at Fordbridge
Park, a residential development with 35 homes for a retirement
community. Many residents are elderly and will be adversely
impacted if this application goes ahead.
·
Have objected to the application on the following
grounds; water supply pollution, flood risk, congestion, noise, air
quality, pollution from dust and impact on quality of life for
residents living at the Park.
·
The biggest concern relates to freshwater supply to
the park which is obtained from an aquifer fed borehole which flows
beneath Watersplash Farm and is the only drinking water supply and
there is no alternative water supply available to the Park.
Confirmed that a new mains water supply could not be
obtained.
·
This aquifer fed borehole must remain and be
regularly tested for possible contamination especially if the
gravel is going to be extracted and filled with clay or other
materials.
Mr
Robin Sider, made representations in objection to the
application. The following key points were
made:
·
Explained that he was a resident and also a
Shepperton Borough
Councillor.
·
Local roads cannot cope with an increase in traffic
this application will generate especially as 30,000 vehicles travel
across Walton bridge onto Walton bridge road every day.
·
A number of HGVs are also travelling to the waste
transfer station close to the application site. This will be six
years of misery to local residents with traffic and noise issues.
The traffic would be detrimental to air quality in the
area.
·
283 objections to this application and also from
Spelthorne Bough Council. Please defer the application for further
investigation under current legislation.
Mr
Mark Kelly, the Applicant, raised the following key
points:
·
A great amount of information has been supplied
alongside this application with preparation for the application
starting in 2009. It has taken over 40 years to get to where we are
today.
·
Permission will still be required from the EA before
work can begin and if the application is approved a great amount of
work will be required before commencement. The site will be
supplying materials to Cemex concrete
plants based in the UK.
·
No objections have been received from statutory
consultees and the site will be providing wealth to the local
economy and has been identified in the Surrey minerals
plan.
·
The site is temporary and will be restored and
enhanced. Extensive traffic modelling has been undertaken and there
will a marginal increase in traffic along the A244.
The
Local Member, Richard Walsh registered to speak on the item and
made the following points:
- Raised concerns around the update to conditions 12 and 20 as
included in the update sheet which was distributed before the start
of the meeting. The Chairman explained that providing update sheets
before the start of the meeting was common practice.
- Speaking on behalf of his residents and is fully supported by
Cllr Tim Evans. Objectors speaking at today’s meeting have
studied the application for the last 2 years.
- Challenge application on basis of possible flooding of local
area which has been demonstrated by previous flooding events of
2014.
- Proposals would tip the balance of serious flooding in
Shepperton. World’s climate is
dramatically changing and the potential damage to residents is
catastrophic. Quality of life for local residents is extremely
impacted by this application and urges to refuse or defer
application on the basis of impact to quality of life.
Key points raised
during the discussion:
-
The report was introduced by
the Deputy Planning Development Manager who gave an overview and
history of the application site. It was explained that 1.2 million
tonnes of gravel and sand would be extracted from the site over a
six year period. It was further explained that it would take at
least two years to get the s106 agreement completed and
pre-commencement conditions discharged before commencement of the
development.
-
A Member of
the committee queried what the implications of flooding would be on
the site and the impact of backfilling clay and imported waste
material on drainage on site. It was queried what the traffic
management in place was and specifically the traffic movement
numbers. It was further queried the archaeological elements of the
pathway that goes through the site and if testing would take place
on this. Reference was made to two planning applications that were
refused in the 1950s and 1960s.
-
The Deputy
Planning Development Manager explained that perimeter swales would be used for surface water drainage.
Modelling had been undertaken and further detail would be required
in the form of surface water and groundwater management schemes
which would require sign off by officers. Planners are satisfied
there are necessary mitigation measures in place. The cumulative
impact of HGV movements has been assessed and vehicle numbers are
greater than 200 but HGV traffic numbers are at 200. Traffic
movements to the Eco-Park have also been assessed in the road
traffic assessment. Pollution matters will be controlled by the EA
but the council has duplicate measures in place and conditions
around contamination which will be closely monitored. All phases
for noise have been assessed and conditions 16-18 cover noise
requirements. An archaeology scheme will need to be submitted as
part of a condition which will identify any archaeological elements
on the site. With regards to why the applications had been turned
down previously, it was commented that the Committee must deal with
the application in front of them.
-
A Member of
the Committee queried what the legal position was on the
freshwater supply to the
Fordbridge Park which was obtained from
an aquifer adding that he was not concerned about the traffic to
and from the site as the number was normal in comparison to similar
sites.
-
A Member of
the Committee expressed the need for planning reasons to be used
before any refusal or deferral is recommended. Paragraphs 68-69
include a summary of flooding evidence submitted by the relevant
experts.
-
The Chairman
asked what work and research the Local Lead Flood Authority (LLFA)
had undertaken and what safeguards were in place for the
aquifer and possible flooding
incidents. The Senior Flood Risk and Network Resilience Officer
explained that he did not initially assess the application which
was approved by a colleague. It was felt that high level surface
water was acceptable under the NPPF and non-statutory technical
standards. The surface water flooding is what the council assessed
and the proposal would be for a swale surrounding the site with the
capacity of the proposed swales being over 3000 m3 and the
requirement for surface water run off being 1800m3. There is a
large difference in what is being proposed and what was actually
required. The Senior Flood Risk and Network Resilience Officer was
content with the proposals. Bespoke conditions had been set and
additional information would be required if permission was
granted.
-
The Project
Manager from Peter Brett Associates (PBA) explained that he had
been involved with the site since 2012. With regards to
groundwater, the applicant produced a groundwater model which was
challenged and tested by PBA and at each stage of the process
parameters were tweaked. It was explained that every parameter was
chosen to be conservative as possible. On that basis, there was a
predicted increase of groundwater level of 230mm on the north-west
of the site. The Project Manager was satisfied modeling was good
and based on mathematics. The predicted increase of groundwater
level of 230mm on the north-west of the site was of concern and
hence a recommendation has been imposed on groundwater monitoring.
The Project Manager advised Surrey that he was content with the
groundwater monitoring work.
-
It was
stated that Surrey had recently declared a climate emergency and if
this application could be deferred in light of this under current
rules and regulations. It was explained that the application was in
accordance with the development plan and there were no grounds to
refuse.
-
Another
Member of the committee was concerned that 45 conditions had been
listed in the report and was of the opinion that if flooding was to
occur this would ruin people’s lives. Following this a
committee Member stated that he was comforted that there were 45
conditions in place and would be concerned if there were any
less.
-
Concerns
were raised in relation to the aquifer which supplied water to
Fordbridge Park and how this would be
dealt with going forward. The Deputy Planning Development Manager
stated that pollution fell within the remit of the EA and controls
were in place to monitor contamination, groundwater and surface
water. It was explained that details of these schemes could come
back to the Committee for consideration if the Local Member wished.
The Project Manager added that placing clay in the aquifer had the
potential to divert the water flow and water would need to find its
way around the site which has been shown in the applicants
modelling. The Project Manager believes the model is conservative
and explained that PBA had suggested that a groundwater monitoring
borehole should be placed on the site boundary nearest to the park.
The Deputy Planning Development Manager explained that there is no
requirement to provide an alternative water supply.
-
There was a discussion if
this application could be deferred on emerging policies.
TheDeputy Planning Development Manager stated that the
application was in accordance with the development
plan.
-
The Chairman
explained that decisions made had to be based on planning decisions
and asked Members if they had any planning reasons for deferring or
refusing this application. A Member of the Committee stated that
she was concerned that the water supply to the Park would be
adversely effected by this application.
-
The Planning
Development Manager suggested that there was a potential to add a
clause to the Section 106 agreement which would need to be agreed
with the applicant but would read ‘for the applicant to
provide an alternative water supply to the park in the event that
it could be demonstrated that their activities had caused an impact
to the quality of the drinking water’. The applicant whom
attended the meeting agreed and accepted this clause by nodding
their head from the public gallery.
-
The Chairman
moved the recommendation to permit the application subject to the
amended conditions in the update sheet and the inclusion of an
additional clause in the Section 106 agreement. There were five
votes for, three votes against and two abstentions. Therefore the
application was permitted.
RESOLVED:
That planning application no. SP12/01487 is PERMITTED subject to conditions and informatives on pages 97-110 of the report
including the amended conditions in the update sheet and subject
to the prior completion of a section 106
legal agreement to secure: a) the long term landscape and
ecological management, maintenance and aftercare of part of the
land at Watersplash Farm; b) the long term monitoring of the
groundwater and c) for the applicant to provide an alternative water supply to
the park in the event that it could be demonstrated that their
activities had caused an impact to the quality of the drinking
water.