To provide an update on the progress of the Electric Vehicle (EV) Charging Point Trials happening across Surrey as the project moves into the final pre-installation phase.
Member approval is required to delegate decision making powers to the Chairman, Vice Chairman and Divisional Member(s) to approve the final five sites upon completion of the consultation feedback review to install EV charging point units.
Decision:
The Local Committee (Waverley) resolved to AGREE to:
(i) Approved the installation of Electric Vehicle Charging points in Summers Road (Godalming), Hale Road (Farnham) and St. Christopher’s Green (Haslemere) in line with the proposals set out in the consultation
(ii) Agreed that Electric Vehicle Charging Points be installed in 1 or 2 of the following: High Park Road (Farnham), Croft Road (Godalming) or Falkner Road (Farnham) in line with the proposals set out in the consultation, and to delegate approval for which sites to progress to the Transport Strategy Project Manager in line with the recommendations by the Chairman, Vice Chairman and appropriate Divisional Members
(iii) Agreed that NO Electric Vehicle Charging Points be installed in Wey Hill (Haslemere), Windrush Close (Bramley) or Brighton Road (Godalming)
(iv) Delegated approval of any future sites required for potential Phase 2 trial to the Transport Strategy Project Manager in line with the recommendations by the Chairman, Vice Chairman and appropriate Divisional Members, where a decision on sites needs to be made prior to the next Local Committee meeting.
Minutes:
Declarations of Interest: None.
Officer in attendance: Steve Howard, SCC Transport Strategy Project Manager.
Petitions, Public Questions/Statements: None.
The item was introduced by the Transport Strategy Project Manager presenting a summary of the consultation responses relating to the recent public consultation on Electric Vehicle Charging points in Waverley (Annex C). Based on these responses, the Transport Strategy Project Manager presented a revised set of recommendations for the Committee to consider (also set out in Annex C) which would enable the progression of supported locations.
Member discussion – key points:
The Local Committee (Waverley):
(i) Approved the installation of Electric Vehicle Charging points in Summers Road (Godalming), Hale Road (Farnham) and St. Christopher’s Green (Haslemere) in line with the proposals set out in the consultation
(ii) Agreed that Electric Vehicle Charging Points be installed in 1 or 2 of the following: High Park Road (Farnham), Croft Road (Godalming) or Falkner Road (Farnham) in line with the proposals set out in the consultation, and to delegate approval for which sites to progress to the Transport Strategy Project Manager in line with the recommendations by the Chairman, Vice Chairman and appropriate Divisional Members
(iii) Agreed that NO Electric Vehicle Charging Points be installed in Wey Hill (Haslemere), Windrush Close (Bramley) or Brighton Road (Godalming)
(iv) Delegated approval of any future sites required for potential Phase 2 trial to the Transport Strategy Project Manager in line with the recommendations by the Chairman, Vice Chairman and appropriate Divisional Members, where a decision on sites needs to be made prior to the next Local Committee meeting.
Supporting documents: