Witnesses:
Liz Uliasz –
Deputy Director for Adult Social Care
Adrian Watson –
Programme Director, Adult Social Care (Land &
Property)
Simon Montgomery
– Senior Programme Manager for Accommodation with Care and
Support Strategy
Kirsty Gannon-Holmes
– Senior Commissioning Manager for Mental Health
Anna Waterman –
Head of Commissioning for Disabilities
Maria Millwood, Board
Director – Healthwatch Surrey
Dan Stoneman –
Head of Commissioning Older People)
Key
points raised during the discussion:
- The Senior Programme
Manager presented slides which provided context to the item (Annex
1) and highlighted the importance of the Accommodation with Care
and Support Strategy (AwCSS) in integrating residents into the
community and having fulfilled lives.
- The Chairman asked
whether the views received in the consultation about sharing with
others were expected. The Senior Programme Manager explained that
the views varied dependent on the client group. For those with
learning disabilities, it was emphasised that they wanted the
choice of living alone or living with others. The shared occupancy
option would have facilities for social workers to be present for
those with higher needs. In terms of those with mental health
issues, single occupancy accommodation would be prioritised as per
the views of the consultation.
- A Member queried
whether the pandemic had an impact on the progress of the AwCSS and
asked about any measures taken to overcome such challenges. The
Programme Director explained that the pandemic had minimal effect
on the early-stage planning of the programme, as they were still in
the preparation stage and conducting due diligence. The greatest
impact was on the Pond Meadow site, as procurement of the project
was delayed. Acceleration and identification of pipeline sites had
continued to take place and the programme was on track to achieve
agreed targets. Additional resources to enable this had been
secured. In terms of Adult Social Care (ASC) support, the pandemic
limited the ability to fully support residents in their new
accommodation.
- A Member enquired
about the impact of the cost-of-living crisis on the programme. The
Programme Director shared that the rising inflation and increased
costs had impacted the cost of construction. Although, financial
planning and pre-market testing had included appropriate provision
for construction-related inflation. The impact on extra care
housing was not known yet. The Senior Programme Manager added that
supported independent living was for those with eligible care needs
and extra care housing was trying to increase the availability of
affordable housing in the sector.
- In response to a
question on the AwCSS’s contribution to the delivery of
Surrey Community Vision for 2030, the Senior Programme Manager
explained that currently there was too much reliance on residential
care which limited independence, especially for those with learning
disabilities and autism (LD&A). Therefore, the Strategy linked
to empowering communities and tackling health inequalities, as well
ensuring no one was left behind. The Deputy Director added that for
those with mental health needs, the Strategy involved helping them
back into employment and independent living.
- A Member asked about
the affordability of the accommodation. The Programme Director
explained that the accommodation would be fully funded through
housing benefits, however, each setting would be subject to the
local rates. Measures had been taken to make settings as cheap to
run as possible, through adopting the Council’s
sustainability ambitions. The Chairman asked whether there would be
a requirement for external providers to comply with the level of
housing benefits. The Senior Programme Manager explained that the
providers were already working with housing benefits organisations
and the Programme Director added that the market lease arrangements
would stipulate it was based on housing benefit levels. If the
operating costs of the building were not met through the housing
benefits, that burden would be on the Council or the provider to
meet. The Head of Commissioning explained that there had been
extensive work with providers, social landlords, and District and
Borough officers to look at housing benefit levels in respect of
the cost of living. Utility costs were built into the arrangements
and the work was linked in with the wider housing strategy across
Surrey.
- Responding to a
question on meeting a variety of accessibility needs, the Senior
Programme Manager explained that in the design process they worked
closely with residents and occupational therapists to ensure that
settings would be designed to meet a range of accessibility needs.
The Member also asked whether there were plans to utilise any of
the former anchor care home sites. The Programme Director informed
Members that all available Council assets would be explored and
proposals utilising a number of existing assets would be brought to
Cabinet. At this stage, the specific sites could not be named due
to confidentiality.
- A Member highlighted
the benefits of utilising Council-owned sites when receiving
planning permission and raised potential issues of going through
local planning committees. The Programme Director explained that
for extra care sites, they were de-risking by seeking outline
planning permission first. A Regulation 3 Surrey County Council
planning-led approach was being taken for extra care and supported
independent living sites; however, it may not be suitable for every
setting. Thus far, there had been a supportive approach from
District and Borough councils.
- A Member asked about
the Surrey-wide Support and Care Commissioning Strategy and how
this would help to reduce health inequalities. The Senior Programme
Manager explained that the Strategy would look at creating a
consistent approach across the County to the commissioning of
future extra care housing settings. It would cover all aspects
involved in the delivery of dedicated Care Quality Commission (CQC)
regulated services which provided a 24/7 on-site presence to
respond to emergencies and meet the assessed needs of residents.
The Strategy would reflect the fundamental purpose of extra care
housing of providing support and security to residents to continue
to live in a home of their own in a community which was responsive
to their needs.
- The Chairman asked
about how it would be ensured that residents could afford the
charged, communal facilities. The Senior Programme Manager shared
that there were examples of best practice regarding communal
facilities and they were working closely to the HAPPI principles.
Accommodation would be located in areas with good transport links
and in a community, as well as ensuring privacy and space. The
Deputy Director explained that the ambition was for residents to be
able to access opportunities such as, work and volunteering. The
Programme Director added that the housing management function would
be provided as part of the service charge. Some additional services
would cost extra, such as, the hairdressers. The services which
would be included or excluded would be defined in the development
stage, following resident focus groups.
- In response to a
question on the collaboration with District and Borough Councils,
the Senior Programme Manager explained that the Council worked well
with District and Borough colleagues and a Housing Partnership
Management role had recently been recruited to. The programme
prioritised care needs over housing needs, however, the housing
partnership work was critical. The Programme Director explained
that structures were in place to deliver the programme. There were
some challenges due to levels of resourcing at different Councils,
but there had not been blocking. There were healthy and challenging
debates at partnership meetings.
- The Chairman asked
about the progress of the procurement process for the support and
care provision. The Senior Programme Manager explained that it was
on track and the procurement process would be completed within a
suitable window. The Programme Director shared that the first phase
development was with Pond Meadow Limited, and they were helping to
shape the timings and processes to ensure that there was a suitable
model in place, and there were no settings without the appropriate
care in place. The Chairman queried whether there had been any
considerations to build accommodation into the units for workers in
Surrey. The Senior Programme Manager explained that at the current
stage it was focused on adults with eligible care needs, with the
ability for carers to stay but not as a form of permanent
accommodation. However, they would look into the possibility of
this in the future.
- Responding to a
question on the outcome of the planning application for Pond Meadow
site, the Programme Director explained that Guildford Borough
Council validated the planning permission on 23 September 2022 and
there was a 13-week determination period. Thus, it was expected
that planning determination would be received prior to Christmas.
The Chairman asked about the time allocated to receiving planning
permission in programme timelines. The Programme Director shared
that there were short timescales included in the programme because
of the outline planning approach. The next stage was based on
reserve matters, but this would be known upfront.
- A Member asked about
the decision and impacts of using shorthold tenancies. The
Programme Director shared that the decision was based on industry
standards. It offered flexibility to the landlord and the tenant,
which allowed the settings to feel like a real home. Legal advice
was sought for each setting and alternative arrangements would be
considered if necessary.
- A Member asked about
the confidence that the delivery of the remaining 50% extra care
units would be on target. The Programme Director explained that
there were four phases of the extra care programme. During phase 1a
and 1b, there were six sites which would deliver circa 368 units.
Work was currently underway on phase 2 which involved four to five
sites and officers were confident they were suitable and that the
number of units in the sites could deliver against the Strategy.
100 to 125 units were required in phase 3 to achieve the target and
sites were being identified and engagement had started with
District and Borough colleagues. The Programme Director was
confident that phase 3 would be achieved. The Member and Chairman
noted the importance of proximity to transport links and the
geographical spread of sites across the county. The Programme
Director reassured Members that settings would not be developed in
locations where there were not suitable transport links. The aim
was for best geographical spread that could be achieved, relative
to site availability.
- In response to a
question on the criteria for eligibility for supported independent
living for individuals with LD&A, the Senior Programme Manager
explained that the primary cohort was those with eligible care
needs. The Programme was intended to reduce the reliance on
residential care, thus, individuals in those settings would be
prioritised. The Deputy Director added that individuals would
receive a Care Act Assessment to understand their needs prior to
allocation to a setting. The Head of Commissioning for Disabilities
added that following an assessment, a detailed care package would
be put out to brokerage. The Deputy Director shared that there
would be a review shortly after an individual moved into their
accommodation to assess whether the level of need was suitable.
There would be constant monitoring through the provider and reviews
would occur as and when needs changed.
- The Board Director of
Healthwatch Surrey queried whether there would be differentiation
between autism specific needs and learning difficulty needs. The
Head of Commissioning explained that they would be considering
potential sensory overload and understanding that some autistic
individuals would benefit from being around their peers, whereas
others would prefer to be alone. The geographical location would be
taken into account, such as, being next to a church that produces
loud noise may not be suitable.
- A Member asked about
gaining data of the cohort of those with LD&A who were
currently supported by their family. The Head of Commissioning for
Disabilities explained that the LD&A Joint Strategic Needs
Assessment (JSNA) would provide a better understanding of the data
available. There had been an increase in need and numbers
post-pandemic. There was a separate JSNA on neurodiversity to learn
more about the needs of that cohort. Surrey Carers Partnership
Board has been refreshed and there was a sub-committee to look at
neurodiversity.
- In response to a
question on the challenges with repurposing residential care
settings, the Senior Programme Manager explained that officers
worked closely with existing providers of residential care and the
challenges were regarding the structure of existing buildings and
whether they were suitable to be reconfigured. There was also work
with providers around the behavioural piece of adjusting from
residential care to supported independent living.
- A Member asked about
whether the increase in the mental health need due to the pandemic
had created greater demand for supported independent living
accommodation, and what kind of support could be expected for those
residents. The Deputy Director explained that there had been an
increase in referrals to teams which included increased complexity
of needs and new cohorts. This had translated to an increase in
requests for supported independent living. In terms of support,
this would focus on helping people back towards independence,
through finding employment and reintegrating into the community. It
would also include teaching individuals to recognise when they were
in crisis. There would be collaboration with Surrey and Borders
Partnership and the voluntary sector for early identification and
preventative work.
- The Chairman asked
about the criteria for providers to be involved in the programme,
such as, prior performance records. The Deputy Director explained
that there would be contract monitoring and there would be key
performance indicators and criteria that they would need to meet.
Previously, the Council had supported a provider to close due to
poor quality of work. The Senior Commissioning Manager added that
it was difficult to get good data on providers, especially if they
were new to supported independent living provision. Therefore,
officers would visit new providers prior to bringing them onto the
framework. Once established, information would be received from
frontline staff and there would be quarterly performance monitoring
meetings with providers. They were in the process of developing a
more detailed quality assurance framework and have visited
providers to meet service users and receive their feedback. The
Board Director of Healthwatch Surrey explained that it can be
difficult for vulnerable clients to know how to report issues. The
Senior Commissioning Manager explained that in order for a provider
to get onto the framework, they would need to have mechanisms in
place to allow users to voice their concerns.
- A Member asked about
how the effectiveness of the partnership working would be
determined and whether it would be successful in delivering a
patient led approach. The Senior Programme Manager explained that
it was about co-designing and co-producing with residents and
routinely capturing feedback and outcomes from services. If the
programme was delivering outcomes, then that would evidence that
partnership working was successful. The Head of Commissioning for
Disabilities added that there were meetings every other month with
the Learning Disabilities and Autism Partnership Board. There were
also mechanisms in place to ensure the work was patient-led, such
as, commissioning being linked to Care Act Assessments.
- A Member asked about
the mitigating actions taken to minimise challenges to delivery.
The Programme Director explained that an assessment had shown that
they needed to improve officer resources to deliver the capital
strategy, and this was a key risk area. A mitigating action taken
was recruiting the Programme Director. High amount of supplier and
provider engagement was crucial for effective delivery. In terms of
de-risking the Council assets, they were seeking and achieving
outline planning permission.
Actions/requests for further information:
For
Accommodation with Care and Support Strategy Leads at Surrey County
Council:
- To organise site
visits for Members of the Adults and Health Select Committee to
Extra Care and Supported independent Living Sites.
- To Hold a meeting
with the Chair and Vice-Chairmen of the Adults and Health Select
Committee and the Chairman of the Surrey Carers Partnership
Board.
Recommendations:
For
Accommodation with Care and Support Strategy Leads at Surrey County
Council:
1. To ensure that Extra Care and Supported
Independent Living Accommodation is genuinely affordable in line
with welfare benefits for individuals who qualify for such
accommodation, and to provide a future written update to the
Adults and Health Select Committee on this.
2. To develop explicit plans on the specific and
specialised facilities that will be available within the context of
the Extra Care and Supported Independent Living Facilities/sites,
and to provide a future written update to the Adults and
Health Select Committee on this, including on what is included in
the rent and what is chargeable.