Witnesses:
David
Lewis, Cabinet Member for Finance & Resources
Leigh Whitehouse,
Deputy Chief Executive and Executive Director of
Resources
Anna
D’Alessandro, Director of Finance – Corporate and
Commercial
Key
points raised during the discussion:
- The Deputy Chief Executive and
Executive Director of Resources introduced the report and
provided Members with a brief outline. It was noted that the
purpose of the report was to provide a status update following the
MySurrey ‘go live’ date and particularly to focus on
the process for capturing lessons learnt. Members noted that the
Digital Business and Insights Programme (DB&I) was to implement
a new Unit4 Enterprise Resource Planning (ERP) system (now known as
“MySurrey”), as a replacement for the previous SAP
system. Details on the context of the item were included within the
published report.
- A
Member noted that the Council’s plan was to discontinue the
use of SAP in December 2023. With regard to external organisations,
such as multi-academy trusts, which were being transitioned from
the Council’s SAP system to other providers, the Members
asked whether Officers were on track for the transition to be
completed by the end of December 2023. The Director of Finance
– Corporate and Commercial confirmed that in May Cabinet had
made the decision to off-board the multi-academy trusts and
academies from the council’s payroll system and that they
would be supported by the Council with the onboarding of their own
payroll system. The Director stated that the project was on track
with agreed timeliness and that the Council continued to support
the programme by providing essential resources and
expertise.
- The Chairman asked the witnesses for their view on whether the
SAP contract would need to be extended beyond December 2023. The
Deputy Chief Executive and Executive
Director of Resources responded that the Council held a perpetual
licence for the software, which would allow it to use the software
on an ongoing basis. However, there was an additional annual fee to
have software support available which was due to end in December
2023. The witness explained that SAP was currently only being used
for school payrolls during their transition to other providers, as
previously noted, and that the SAP software would become redundant
once those transitions were complete. In relation to a contingency
plan in the event that the software was required following December
2023, Members noted that the replacement software, MySurrey, went
live in June 2023 and so the SAP system would only need to be used
during the transitional phase for external organisations and for
data archiving purposes.
-
The Deputy Chief Executive and Executive Director of
Resources explained a ‘Lessons Learnt’ exercise would
be completed as part of the transition to ‘business as
usual’ and the closure of the DB&I programme.
-
Members noted the explanation that the main reason
for school payroll issues in September 2023 was due to a technical
issue related to incomplete forms relating to data capture being
entered into the system. Members also noted that the main issues
with the new system related to technical issues,familiarisation/process, and potential changes/refinements as noted within the
report.
-
Members discussed the new
requirement for Officers to submit receipts when making an expenses
claim. Some Members stated that they were unsure why the previous
process did not require receipts as evidence for a claim. SAP
required expense receipts to be kept for internal audit purposes
but were not required to be attached to claims on the
system.
-
A Member queried the process
followed to procure the new system. The
Deputy Chief Executive and Executive Director of Resources
explained that, following testing, the decision was made to seek a
cloud-based system that was based on a set of detailed requirements
which suppliers then responded to and then a preferred provider was
selected.
-
A Member asked whether witnesses could quantify the
additional financial spend on MySurrey to date for the Committee
and any other costs incurred by other Council services as a result
of its implementation. The Deputy Chief Executive and Executive
Director of Resources explained that the total estimated cost of
the programme was initially submitted to Cabinet and then further
subsequent revised estimates were submitted. It was noted that
impacts in some other Council services were not able to be
quantified as they had manifested themselves in different ways. The
original programme budget that was considered by Cabinet in 2020
was around £17 million and then, following two subsequent
increases, the total was around £27 million. A Member said
that they consider an overspend of around £10 million as
staggering and asked for detail around accountability for the
overspend. The witness explained a programme stakeholder board and
Programme Director governed the programme, but the ultimate
responsibility sat with the Programme Sponsor.
-
Regarding the benefits of the programme, a Member
said they believed a report to Cabinet stated that there would an
annual saving of £6.5 million. As the programme was delayed
by two years, the Member asked whether that meant an additional
loss of savings of £13 million over a two-year period. The
Deputy Chief Executive and Executive Director of Resources stated
that he did not recognise the £6.5 million figure and asked
to come back to the Member outside the meeting. In addition to
this, the witness said that he did not want to pre-empt the lessons
learnt conversations, but he believed that the original timeline
for the programme was over ambitious.
-
In regard to the Intelligent Client Function (ICF) body, a Member
asked for detail on its membership and proposed governance around
it. The Director of Finance – Corporate and Commercial
explained that the Intelligent Client Function was a best practice
function established after the implementation of a large and
complex system. The ICF would follow a contract management and
strategic approach to support the optimisation of Unit 4. The
function would sit within the Corporate Finance service but would
have strong relationships with IT&D and Procurement. Officers
were aiming to commence in May 2024 and interim arrangements were
being considered in the meantime. A Member requested that full
details of the ICF were considered by the Committee when
available.
-
The Chairman stated that there was
concern from Members of the Select Committee on what had been
discussed during the meeting, and for future IT&D projects, and
highlighted that the topic would be considered by a task and finish
group.
-
The Select Committee agreed the
recommendation ‘that the Resources and Performance Select
Committee convene a task group of three to five Members to
undertake the review of the MySurrey project with a view to report
to the select committee at its first meeting of 2024’. The
Chairman further noted that he expected full cooperation with the
task and finish group and support from the independent
consultant.
Actions/requests for further
information:
Deputy Chief
Executive and Executive Director of Resources to clarify the figure
reported to Cabinet regarding how much MySurrey was forecast to
save annually.
Resolved:
That the Resources and Performance Select Committee
convene a task group of three to five Members to undertake the
review of the MySurrey project with a view to report to the select
committee at its first meeting of 2024.