Witnesses:
James Clarke, Frimley
Health Chief Strategy Officer (Frimley Health NHS Foundation
Trust)
Cain Thomas, Interim
Programme Director, New Frimley Park Hospital Programme (Frimley
Health NHS Foundation Trust)
Carol Deans, Director,
Communications and Engagement (Frimley Health NHS Foundation
Trust)
Sam Burrows, Chief
Transformation, Delivery and Digital Officer (NHS Frimley
Integrated Care Board)
Ellie Davies,
Associate Director, Communications and Engagement (NHS Frimley
Integrated Care Board)
Key
points raised during the discussion:
Update on the current situation at Frimley Park Hospital [Item
6b]
Key
points raised:
Government review and
internal leadership changes
- The Chief Strategy
Officer explained that the government announced a comprehensive
review of the New Hospital Programme. Signals received so far were
around continuing the programme as normal. At the Prime
Minister’s Questions on Wednesday 4 September, it was
confirmed RAAC hospitals were still a priority. There were internal
leadership changes, with Lance McCarthy as the new CEO and Caroline
Hutton as the new Senior Responsible Officer for the New Hospital
Programme. Work was being undertaken to understand what changes
would potentially be needed as part of the announcement. The new
hospital remained a priority.
Reinforced Autoclaved Aerated Concrete (RAAC) Works
- The Chief Strategy
Officer outlined that work undertaken on RAAC was likely to last up
to around 2030 and were not intended to be a permanent fix. By end
of 2024/25 nearly £30 million would be spent on
reinforcements to make the current hospital site safe. Disruption
to patients during these works is significant during works. For
example, the paediatric ward was currently being reinforced and
therefore closed. It had to be ensured that the patients were moved
to an appropriate place. Remedial work was also done on operating
theatres, all of which could not be removed simultaneously, and
therefore needed a phased approach. Structural engineers were on
the current hospital site bi-weekly to continue inspections, on an
ongoing basis.
Essential new wards and breast cancer diagnostic
facility
- The Chief Strategy
Officer brought attention to Frimley’s new inpatient and
diagnostic facility, which was a £49 million investment into
the current site. This would provide additional capacity of 74
inpatient beds. It was set up under modern hospital principles,
such as single rooms and bays, with a dedicated breast care
diagnostic and outpatient unit. This facility would open in early
2024 and help with the hospital’s current demand.
Current access issues and plans
- The Chief Strategy
Officer outlined that a main challenge with the current hospital
site was travel, parking and access. Frimley Park Hospital had
off-site parking on Lyon Way which was an approximately ten-minute
walk to the hospital. Staff parking had been relocated to Lyon Way
for more capacity on the hospital site. Work was being done
collaboratively with partners to ensure patients were not brought
on site unnecessarily, such as through virtual appointments,
patient-initiated follow-ups, and community diagnostics. Work was
continuing on what could be done to make travel to the hospital
easier.
System wide urgent
care
- The Chief
Transformation, Delivery and Digital Officer outlined that when
urgent care services were planned and delivered, NHS Frimley
Integrated Care Board (NHS Frimley) tried to ensure it was
joined-up, that patients had timely access to the services and
received the appropriate care. Access that patients received
outside of hospital, as well as access to emergency departments,
was important with more than 90% of NHS patient contact occurring
outside of a hospital environment.
Therefore, there was a continuing focus for urgent care on a range
of service developments including how patients could access
services with General Practitioners, alternative primary care
appointments through the Pharmacy First scheme, urgent care
centres, same-day access hubs, and ensuring that 111 calls were
answered promptly, and patients were subsequently referred to the
right service. Work was done closely with colleagues at Frimley
Health NHS Foundation Trust (Frimley Health), South Central
Ambulance Service and Southeast Coast Ambulance Service to ensure
that when 999 or ambulance care was required, that timely access to
those services were available. NHS Frimley continue to understand
what access was required for the new hospital, to ensure that new
services would be as beneficial as possible for local
people.
Update on
the progress of the hospital and site selection process [Item
6a]
Key points raised:
Background: site selection process
- The Interim Programme
Director provided a brief overview of the site selection process.
When the Trust secured their place on the New Hospital Programme in
May 2023, a land agent was appointed to identify a list of
potential sites. A hurdle criteria was then set, such as whether
there was a landowner willing to sell, if the site was big enough
and whether there were any planning and programme risks. This
criteria led to a priority list of sites. An evaluation criteria
was applied on 14 different areas alongside continual application
of the due diligence measures, which resulted in the preferred
site. The site selection process aligned to HM Treasury’s
Green Book. Frimley Health NHS Trust had recently visited the
national New Hospital Programme’s headquarters and completed
a peer review of the site selection process, which was
well-received.
What are we doing now: technical due diligence
- The Interim Programme
Director outlined there was a large team of professional advisors
and subject matter experts helping with the due diligence to ensure
the New Hospital Programme moved at the right pace, that the right
site was found and an ability to progress to a detailed design
process. A key risk schedule of each preferred site and the
opportunities was developed in Summer 2024. Evaluation criteria
included transport, environment, ecology, flooding, planning, the
overall programme, air quality, utilities diversion, utilities
connections and construction logistics. Design and Implementation
was being undertaken, in terms of developing a master plan for the
preferred sites. The National New Hospital Programme’s
Hospital 2.0 template was available to see the impacts for the new
hospital. Information from the due diligence could be reviewed in
the context of the different sites and the challenges, such as
external infrastructure upgrades and ecology improvements. The
relative cost value of the preferred sites was reviewed in Summer
2024, which built a bigger picture for the master plan and what the
indicative cost would be of developing a preferred site
Considering our population & catchment
- The Interim Programme
Director explained that in Summer 2024, understanding of
hospital’s catchment, population and how a preferred site
would impact this was developed. This included travel and access to
the site. This was factored into the site due
diligence.
- The Chief
Transformation, Delivery and Digital Officer added that as part of
the Public Sector Equality Duty and the Health and Care Act (2022)
there was a legal duty to undertake an Equality Impact Assessment
(EIA) to understand and consider the impact that changes made to
services had to NHS Frimley’s population. NHS Frimley, as a
partnership of organisations, aimed to go beyond the legal minimum
duties. NHS Frimley had a stated strategic intent, in the
Integrated Care System’s (ICS) strategy, around reducing
health inequalities and improving healthy life expectancy. NHS
Frimley used a range of data, intelligence, the Joint Strategic
Needs Assessment (JSNA) and ongoing engagement with local people to
build understanding of the population. NHS Frimley would examine
this data throughout the site selection process to understand the
benefits and mitigations that may be required for any change that
would be progressed. This would be produced as part of an
Integrated Impact Assessment. This work was an ongoing and evolving
exercise. Work would continue with partners, including the broader
public sector, elected representatives, staff, and local
people.
Working with relevant Local Planning Authorities
(LPAs)
- The Interim Programme
Director explained that progress was made by working with Local
Planning Authorities (LPA) to discuss the implications to the
preferred sites. Under the Planning Performance Agreement, NHS
Frimley had progressed through a pre-application process and
presented master plans to LPAs to discuss implications of
developing a new hospital on the preferred sites. This was done
confidentially, due to the simultaneous commercial dialogue with
preferred sites. The programme was moving towards a situation where
a Heads of Terms agreement could be formed and enter a contract to
acquire a site after the completion of the site selection process.
Confidentiality was important as the preferred sites had businesses
on them which needed to be protected whilst commercial negotiations
were undertaken. Significant progress had been made with each of
their preferred sites with the LPAs.
Engaging County Highways Authority (CHA)
- The Interim Programme
Director noted that good progress was made with the County Highways
Authority (CHA). A transport assessment was completed and issued to
the CHA. Sustainability of road access was reviewed and an
assessment on how road networks had capacity for future use and
active transport movements. Detailed junction modelling was done on
each preferred site and proposed entrances to see how it would
withstand additional transport movements. There were some junctions
and areas in the local vicinity of the preferred sites that was at
capacity and would need significant infrastructure upgrades. The
integration of existing transport networks into preferred sites was
reviewed. When moving to a detailed planning application, Frimley
Health NHS Trust would need to work with the CHA and LPAs to ensure
a smooth and successful planning application.
Next Steps
- The Interim Programme
Director explained that the pre-application conveyed a need to look
more at the ecology and environmental aspects. Time was being spent
to work on this, in terms of reports received from LPAs, to
understand how to mitigate and improve the ecology and
environmental impacts of developing the new hospital. The catchment
analysis and the population impact, such as travel to the new
hospital site was being further investigated.
- The Chief Strategy
Officer added that Frimley Health NHS Trust was committed to
working with the committee as the New Hospital Programme
developed.
Questions
- The Chairman asked
what impact the lack of operating theatre capacity was on backlogs,
and what recovery there was to reduce the backlog. The Chief
Strategy Officer acknowledged that waiting lists were too high, in
the region of around 80,000. There were lots of plans to reduce
this quickly. Theatre capacity was a problem. The opening of the
Frimley inpatient and diagnostic facility would provide 74
additional beds. This would help theatre teams, as the beds and
flow to get people through operations that was also an issue. There
was Heatherwood Hospital, an elective care site that operated six
days a week. Getting this to seven days a week was being explored.
The theaters ran at about 85% capacity, but Heatherwood Hospital
provided more opportunity to get patients into what was known as a
‘cold site’, so patients know their elective surgery
would not get cancelled on the day for an emergency.
- A Member asked
whether a site for the new hospital had been found. The Member also
raised the issue of car parking and suggested a park and ride
service from the current hospital site. The Member raised that
Queen Elizabeth Hospital in Glasgow had tried single rooms and
found it difficult, partly because it was not well built, and that
the hospital was not prepared for the system. The Chairman strongly
suggested that having a bus service to move people to would be a
good idea and moving people with minor injuries over to a minor
injuries unit would be a sensible thing to do, and asked how much
longer the process would take before the new site is revealed, and
by when. The Chief Strategy Officer noted that park and ride was a
good idea. There was commitment to find a solution and explore
appropriate options. In terms of the new hospital’s design,
it followed a set process which was a Hospital 2.0 design. It was
suspected that Frimley Health NHS Trust would have a chance to
learn about single wards from the new diagnostic and inpatient
block opening in January 2025. Single rooms provided benefits to
patients, such as reducing infection spread, a quieter space and
privacy. Nursing teams, health professionals and doctors would need
to work differently.
- The Interim Programme
Director explained that several sites had been found that had the
ability to accommodate the new hospital. It was not easy to find a
site within five miles of the existing site. The process had to
occur at the right pace. Due diligence on the potential sites was
continuing. In terms of park and ride, that arose in discussions
with the LPAs. This would be looked at further, but the development
on the green travel plan had not yet started, which would inform
how parking would be dealt with on the hospital site. In terms of
the single rooms, there was a hospital 2.0 template from the
national team which was single rooms and 32 bed wards which was
asked to be accommodated within the new hospital. This would be a
significant change of culture in terms of operating policies and
management of the hospital wards. The national team took advise
from the royal colleges and clinicians to ensure the design was
compliant, viable, and implementable. Regarding the transport
network, modelling was undertaken on each of the sites to know when
networks had reached capacity. Work was being undertaken to
understand the travel times of patients and staff from various
locations and how journey times could be managed regarding an
active travel plan.
- The Member raised
that there must be a plan and date by which a new hospital site had
to be chosen and emphasised that building had to start in 2026. The
Member also raised the need for engaging with staff at Frimley Park
Hospital about the running of the new hospital. The Member also
stated the importance of keeping staff on the ground informed about
how they want to see the running of this new hospital, and whether
the planning has been able to start to allocate staff
accommodation, so the committee are assured that staff can live
there or stay there in a reasonable way.
- A Member asked if
there was a previous figure that the government suggested they
would finance the new hospital for, and if so, what that was, and
whether this had subsequently changed during the site selection
process. Regarding the new planning policy framework, which
included increasing the housing targets for most local authorities,
which created the assumption of a bigger population in the future,
the Member asked if this was being considered as to calculated
capacity. The Member re-emphasised the need to obtain a figure of
when a date would be revealed to give people confidence the
programme was on target.
- Regarding the status
of the site selection process, the Interim Programme Director
explained there had been a lot of detailed work undertaken, but the
team was not yet able to conclude the process. There was not a
definitive date of when the process would be completed. There were
several areas still being reviewed such as the commercial
negotiations and areas arisen from the pre-application process.
Time was needed to get this right.
- Regarding the
programme’s overall delivery, the Interim Programme Director
explained that building starting on the new hospital in 2026 to
achieve the 2030 deadline, remained the case. Work completed in
Summer 2024 had indicated that the programme was still on-track to
achieve this. When Frimley Health would start to review the design
of the new hospital and map clinical pathways of where all the new
hospital’s departments would go, there would be an engagement
exercise with clinicians and all user groups to ensure feedback was
considered and the design was correct, both from a staff and
patient perspective. The demand and capacity modelling was still
being finished to inform the size of the new hospital. This would
feed into a funding envelope confirmed by the national programme.
The pre-election period and change of government meant Frimley
Health NHS Trust were not yet aware of the funding envelope but
they continue to work towards the breif.
- The Member asked if a
figure of the funding for the programme could be given. The Interim
Programme Director explained that Frimley Health would not be aware
of the figure until after the New Hospital Programme’s review
and clarified that Frimley Health NHS Trust was awaiting the
affordability envelope. Frimley Health NHS Trust was working to a
size of 130,000 square metres previously for the new hospital and
the cost associated with that. A Member raised that the figure was
thought to be £1 billion. The Interim Programme Director
explained that it was originally over £1 billion, but that
was from several years ago. Inflation would need to be considered
and an update of how the review of the New Hospital Programme was
concluded. The Director of Communications and Engagement explained
that in the public domain there was a figure of £1.3 billion
early in the programme, from the initial strategic outline case to
get Frimley Park Hospital onto the programme. The size of the
hospital may change this figure, upwards.
- A Member raised a
question around the Government's consultation around extra new
housing targets. The Interim programme Director explained Frimley
Health NHS Trust was aware of the consultation currently being
undertaken, and the implications it could have to the LPAs. Frimley
Health was observing and reviewing the demand and capacity
modelling to study the potential implications of the
consultations.
- A Member asked if the
new hospital’s funding would include road infrastructure
upgrades. The Interim Programme Director explained that if
infrastructure upgrades were needed to facilitate the new hospital,
it would be part of the new funding envelope.
- A Member asked that
when it was announced in the budget on 30 October 2024 which would
infer whether the hospital can go ahead or not, if there were plans
in place for a situation whereby the government’s expected
Autumn Budget turned out to be a lot less. The Interim Programme
Director explained that there was contingency planning and
reviewing of the different sizes of hospitals, in terms of the area
needed.
- The Member asked if
there would be consultation with some of the potential sites to get
feedback and make the community feel more involved. The Director of
Communications and Engagement explained that a commitment was made
at the previous committee meeting around extensive engagement and
consultation. Until the due diligence process was completed,
Frimley Health NHS Trust was not able to know what the engagement
and consultation would be about. The Chief Transformation, Delivery
and Digital Officer added that there was a dependency on the site
location to help inform what the engagement exercise would look
like. The Officer reassured the committee that there would be
significant, ongoing engagement with local people, representatives
and staff looking at a range of options to ensure the process was
being done in the right way. The Member also asked if engagement
included the Bracknell Forest area. The Chief Transformation,
Delivery and Digital Officer confirmed it did and that there would
be continued significant engagement on the
‘where’s’ and the ‘how’s’ of
the delivery.
- A Member asked what
was happening with regards to recruitment and the retention space,
and the people-front. The Director of Communications and Engagement
explained that the answer would be better covered towards the end
of the session in a brief presentation.
- The Chairman
requested that Frimley Health NHS Trust provide a map to the
committee of all their current sites, their purpose and capacity,
and a list of things that were being planned.
- The Vice-Chairman
recognised the importance of the ICB in working on the project and
having hubs and urgent triage treatment centres as part of the
build-up of NHS services up to the opening of the new hospital, and
believed it was difficult to understand the possibility of a
40-to-50-acre site within a five-mile radius of the current
hospital site. Therefore, clarity was needed on the size of the
site. The Vice-Chairman also raised their dealings with commercial
businesses and the subjective view that may suggest that the sites
could be situated within commercial business areas which raises
considerations with regards to transport support, infrastructure,
utilities, and the need for a lot of forward emphasis on the
programme’s timeline.
- The Chairman
expressed a want for more information of a planned date on when to
expect the site selection process to be completed.
- The Director of
Communications and Engagement noted that Officers heard the
committee’s frustration and that this was also felt by
Frimley Health and NHS Frimley’s teams. Many decisions would
be out of their control. The programme could not progress until
further information was received but were also unable to progress
with providing dates due to the parts needed being out of their
control but the work with the LPAs on the potential sites would
help in getting that rich information together. When outcomes were
able to be shared publicly, it would be done thoroughly with plenty
of information.
- The Chairman raised
concern around the programme, the fixed nature of its end date, the
lack of a decision, and a planned date for moving forward. A Member
raised that at the committee’s previous meeting in May 2024,
it was raised that Frimley Health and NHS Frimley expected to
update on the sites by the end of Summer 2024.
Break was called at 3.53pm
Cllr Michaela Martin left the meeting
Meeting resumed at 4.05pm
Co-design [Item 6c]
Key
points raised:
The purpose of
co-design
- The Associate
Director of Communication and Engagement explained it was decided
to propose a co-design element of the programme to inform best
practice. There was commitment to work with patients, staff,
volunteers, local communities and other stakeholders and involve as
many people as possible in all stages of the development. The
purpose of co-design was to inform the engagement and involvement
strategy and build on the established commitment to equality and
accessibility. Additionally, co-design involved understanding how
NHS Frimley’s communities and key stakeholders would like to
be engaged and involved in the New Hospital Programme, to enable a
built strategy that would last the life of the
programme.
Protected
characteristics
- The Associate
Director of Communication and Engagement added that a key element
of achieving the purpose of co-design was to focus on some of the
protected groups of people, such as those that spoke English as a
second language, those with learning difficulties, unpaid carers,
seldom heard communities, parents and young people, and in
particular those from the Military backgrounds to ensure the
facility continued to be right for them. Frimley Health was
committed to hearing from all groups.
Working with Healthwatch
- The Associate
Director of Communications and Engagement outlined that Healthwatch
was a strong partner and there was communication with different
Healthwatch groups that covered Frimley’s area. Healthwatch
would help with the co-design work, with their links in
Frimley’s geography. There would be in-depth conversations
with community group leaders and key representatives of particular
groups. In parallel, a public survey would be run to capture views
of the broader public. Combining this with the in-depth
conversations would result in a robust and inclusive approach to
engagement.
Our
goals of co-design
- The Associate
Director of Communications and Engagement explained that the goals
of the co-design were three-fold and included a strong strategy for
engaging with local people, an increased trust and ownership of the
new hospital project and improved accessibility and
inclusivity.
Deliverables
- The Associate
Director of Communications and Engagement outlined that a full
report and evaluation summary would be produced with the findings
of the co-design work. This would be embedded into the core
activities of the New Hospital Programme to ensure the engagement
and consultation process was comprehensive and
impactful.
We
want your input
- The Associate
Director outlined that there was interest in the committee’s
views and suggestions of the co-design plan, and how this could
continue to be developed ahead of going live in the coming
weeks.
Engagement of the staff at Frimley Park Hospital [Item
6d]
Staff engagement
- The Director of
Communications and Engagement explained that there were 14,000
staff across Frimley Health NHS Trust, just under 6,000 of which
worked at Frimley Park Hospital. Around 1,800 staff were nurses and
midwives, just over 1000 staff were involved with other clinical
support services, 850 were medical and dental staff and around 350
were allied health professionals. 60% of staff lived within a
5-mile radius of the hospital. Around 65% of nurses and midwives,
63% of other clinical services, about 34% of the medical and dental
workforce and around 46% of the allied health professionals lived
within the 5-mile radius of the current hospital site. 77% of 67 to
70-year-olds lived within a 5-mile radius of the current hospital
site. Regarding accommodation for staff, while this was currently
provided it tended to be short-term and not on-site accommodation.
While the impact on housing for staff and future workforce would be
reviewed, the imperative of accommodation being on the hospital
site became more of a potential opportunity rather than a
necessity. A dedicated workforce work stream had been created, with
a role to understand more about staff, their travel needs, future
needs and the impact of the New Hospital Programme on them. Staff
would be involved in the single room design of the new hospital by
informing them of information from the national team on its
importance and the safeguards around it, and ensuring opportunity
was given to input, which could be relayed to the national team. A
priority for Frimley Health NHS Trust was to try to adopt an
attitude of ‘staff first’. There were lots of ways
staff were engaged which would continue, such as a Roadshow of
going round all sites, speaking to staff.
Future engagement activities
- The Director of
Communications and Engagement explained there was a range of
different ways of communicating with staff. Frimley Health NHS
Trust would be looking to develop more in-person events, attendance
at meetings and create named ambassadors within all areas to ensure
staff were aware of news and information.
Questions
- A Member asked how
much of the 14,000 staff at Frimley Park Hospital were from
agencies and how agency staff would be introduced to the new ways
of working with single rooms, sometimes at short notice. The
Director of Communications and Engagement clarified that 14,000 was
the figure for the employed staff, and agency staff would support
on top of this. Frimley Health actively worked to enhance
recruitment and retention, to significantly reduce the use of
agency staff. There were very clear processes on how agency staff
were inducted.
- The Member also asked
how it would be ensured that the new hospital would retain the
fringe basic payment for staff. The Director of Communications and
Engagement explained this had been flagged in the workforce
workstream, but an answer could not be provided yet.
- The Member asked if
there would be co-production meetings with Healthwatch. The
Associate Director of Communications and Engagement confirmed the
intention to co-produce ways in which to engage with people. In
some instances, representatives of groups would be used, but the
aim was to have direct conversations with target groups where
possible.
- The Chairman asked
what discussions had taken place with LPAs around staff
accommodation, considering single rooms and the subsequent need for
more staff and what conversations had been undertaken with the
local authorities. The Director of Communications and Engagement
explained that the programme was not at the point of having these
discussions. Further understanding was needed around what the
impact of the new hospital on the workforce would be, which would
be reviewed by the workforce workstream. The Interim Programme
Director noted it was too early for discussions on staff
accommodation with LPAs. The programme was being reviewed in terms
of a size perspective from the master plan but was not yet being
designed.
- The Chief
Transformation, Delivery and Digital Officer raised that it was
important not to underestimate how impactful the change in the use
of technology was on the projection of the required future
workforce.
- The Vice-Chairman
raised several concerns, and that the ICB’s renewed ambition
strategy, as well as the strategy for NHS England was changing all
the time, and recruitment and retention was going to be difficult.
It was suggested the committee would like to see a video example of
the new type of hospitals using the 2.0 template that were open, to
see key areas such as parking and accessibility to look at how
these were operated.
- A Member asked
whether the Trust had autonomy to decide where the new hospital
site would be or if it had to go through various processes in the
department for approval, and if it was contributing to the delay in
choosing a site. The Interim Program Director explained that the
size of the new hospital would be decided jointly by Frimley Health
and NHS Frimley, with the demand and capacity modelling and
projections. The Chief Transformation, Delivery and Digital Officer
added there was expected scrutiny on what Frimley Health and NHS
Frimley put forward by the Treasury, The Department of Health and
others. There would be a reliance on transformation to make the new
hospital viable for the future. Transformation, better hospital
discharges and reducing a patient’s length of stay in
hospital would result in more beds without needing to build more
beds. More community-based care would mean more beds in community
facilities. Demand mitigation by investing in preventative-based
care, proactive care, and using digital technology such as risks
stratification and population segmentation would make a significant
impact on the demand and capacity model and therefore what facility
is built.
- A Member asked if the
pharmacy model would be updated, as this delays people from leaving
hospital. The Member also asked when the programme would engage
with local teams and local councils to see the available space
options to build community-based facilities. The Chief
Transformation, Delivery and Digital Officer explained that
preventing people from going into hospital in the first place was
the desired objective by keeping them well outside of a hospital.
Work was done around this. For example, 7000 people were on remote
monitoring, which used technology to assess whether people are well
due to a high-risk of hospital admission. There were too many
people waiting too long for medicines before they could be
discharged from hospital. This model needed updating, and using
technology would make a big difference. Access to, for example,
Artificial Intelligence and robotics, for delivering supplies
around a large facility like a hospital, was within reach. It was
hoped the new hospital would make the most of technological
opportunities. Regarding care closer to home, the existence of
facilities at a local level needed to be ensured, which had to be
done in partnership with local councils. Virtual wards also made a
difference to ensure people were kept well without needing a
hospital facility. A Member raised that the social care system
needed to be sorted out before this could be discussed. The reality
of the government funding needed to be considered regarding social
care and a decision was needed at some point.
- The Chairman raised that people leaving hospital
early may impact on primary care, which would need to be resolved
as well. The connection with social care needed to be present,
strong and very effective and all processes reviewed.
- The Vice-Chairman raised concerns that could
make prevention difficult to achieve, such as issues around diets
such as processed food, the spread of viruses such as COVID-19,
norovirus and measles, and the winter season. The Chairman
concurred with the points raised by the Vice-Chairman and raised
the need for strengthened education and public health.
Recommendations:
- We think you need a
contingency plan with a date to activate it in order to make sure
that the population is protected from issues around not being able
to operate the current hospital site.
- There is a need to
thread the provision for accommodation into local housing plans, to
ensure its proper integration within the planning.
- A view of all of
Frimley Health sites and all planned extra sites is a needed part
of the decision-making process. To make this information available
as early as possible.
- A JHOSC Committee
visit to the in-patient and diagnostic imaging facility happens as
soon as possible.
- The JHOSC Committee
needs educating on what the new hospital 2.0 might look
like.
- Needs-modelling: the
Committee would like this information to be shared as well so that
the committee has a good view of what you are considering, what the
modelling process is in some detail, and what that looks
like.
The Committee
NOTED the updates received at the meeting.
Actions/requests for further information:
- Frimley Health/NHS
Frimley to provide committee a copy of their presentation used in
the meeting.
- Frimley Health and
NHS Frimley to provide a map to the committee of all their current
sites, their purpose and capacity, and a list of things that were
being planned.
- Frimley Health/ NHS
Frimley to provide an example of the ‘2.0 template’
hospital, to see key areas such as parking and
accessibility.