Outline application for the erection of part 1, 4, 5 and 6 storey building for extra care accommodation, comprising self-contained apartments, staff and communal facilities, and associated parking with access from St Annes Drive and Noke Drive. Appearance and landscaping reserved.
Minutes:
Officers:
Charlotte Parker, Planning Development Team Leader
Officer introduction:
The Committee was provided with an overview of the report and update sheet. Members noted that the outline application was for the erection of part 1, 4, 5 and 6 storey building for extra care accommodation, comprising self-contained apartments, staff and communal facilities, and associated parking with access from St Annes Drive and Noke Drive. Appearance and landscaping reserved. The full details were outlined within the published report and update sheet.
Speakers:
Carol Bell spoke on behalf of the applicant and made the following points:
A Member expressed concerns regarding the layout and flood risk from a planning perspective. The Member inquired whether the overlay of Zone 3 flooding on the layout had been considered to ensure that no ground floor residential accommodation was located in this area. The applicant’s agent confirmed that the flood risk assessment document had been updated since the final submission, and additional plans were included to show that residential accommodation on the ground floor was elevated higher than the flood risk zone. The Member asked whether the applicant was aware that current government guidance recommends floor levels to be at least 600 millimetres above the estimated flood level, whereas the design put forward in the plans indicates a floor level of only 300 millimetres. Officers agreed to respond during the item’s discussion.
A Member asked for details of any additional parking spaces in the local area. The applicant’s agent confirmed that the council was aware of the parking restrictions near the site and that officers had worked with the Highways department to consider the local provision of public transport to make the site as sustainable as possible. It was further noted that the majority of residents were not expected to own cars, and officers were working to include a ‘car club’ provision to support alternative means of transport.
The Local Member, Jonathan Essex, made the following points:
In regard to design, officers stated that it may be difficult to require any additional design to meet passive house design criteria. The officers added that it may be possible to include an informative, but that it could not be conditioned.
In regard to liaison with the local school, it was confirmed that the condition did take into account the movements of the school children. However, it was noted that it was unclear whether further action could be taken at this stage. It was suggested that an additional provision could be included, ensuring that, during the construction phase, there would be a dialogue with the school to facilitate a smooth and safe process for the children.
It was noted that the development of the other part of the site was the responsibility of the landowner and applicant. While there had been some discussion regarding community use, particularly for young people, the officer expressed hesitation in suggesting specific plans or a route through the relevant part of the site. However, it was mentioned that, if the wider site’s plans progressed, there could be an opportunity to integrate plans with the current application during the reserved matters phase.
Key points raised during the discussion:
1. In regard to concerns raised regarding Flood Zone 3, officers stated that the guidance suggested a finished floor level of up to 600 millimetres in areas of high uncertainty regarding flood risks. However, detailed modelling had been conducted for this application, as outlined in the flood risk assessment, providing a reasonable degree of certainty about the potential extent of flooding. Under these circumstances, the 300 millimetre level was considered acceptable. The Member stated that she still had concerns with the flood risk on the ground floor.
2. A Member stated that he supported the proposal and stressed the need for applications to make the best use of the land.
3. A Member raised concerns with accommodation being built on the ground floor due to the risk of flooding.
4. A concern was raised regarding Condition 7, which stated that details of a flood warning and evacuation plan were to be submitted to and approved by the local planning authority prior to occupation of the building, with implementation thereafter. The Member expressed that, based on the discussions, they would feel significantly more comfortable if the condition required submission before commencement of the development rather than prior to occupation. In response, officers stated that the guidance on pre-commencement conditions strongly recommended avoiding them unless absolutely necessary. The officer explained that a flood evacuation plan could be submitted prior to occupation, as the trigger for the plan was the presence of people on the site, rather than the commencement of physical works. In response to concerns raised by Members, it was emphasised that the evacuation plan would need to address the 24/7 residential use of the site, ensuring pre-emptive actions were included and that safe egress during a flood event was accounted for. The managed nature of the facility was highlighted as beneficial, as it allowed for better oversight of the evacuation plan compared to private residential settings. The officer expressed that, in their professional view, it was acceptable for the condition to be prior to occupation.
5. The Chairman moved the recommendation, with agreement that reserve matters would return to the committee for consideration, which received 7 votes for, 1 against, and 1 abstention.
Actions / further information to be provided:
None.
Resolved:
That, subject to Regulation 3 of the Town and Country Planning Regulations 1992, outline planning consent is granted for application reference: RE24/00028/CON, subject to the conditions outlined within the report and update sheet.
Supporting documents: