Issue - decisions

Waste Contract and Delivery of the Eco Park

29/04/2015 - Amendment to Waste Contract to deliver the Waste Strategy

1.         That all the necessary preconditions identified in the Cabinet report of 23 July 2013, as outlined in paragraphs 3 - 34 of the submitted report, have now been met.

 

2.         That the assessment of the Director of Finance is that the cost of proceeding with the Waste Strategy, including the Eco Park, meets the value for money criterion and is the most affordable option available to the council.

 

3.         That the council proceeds to issue the second Notice To Proceed (NTP2) in accordance with the contractual processes approved by Cabinet on 30 October 2013.

 

4.         That the corporate revenue budget refresh in July 2015 will take into account the budgetary effect of delivering the Waste Strategy, including the Eco Park.

 

5.         That the Strategic Director of Environment and Infrastructure puts in place the governance arrangements described in Annex 2 of the submitted report, and provides quarterly reports to the Cabinet Member for Environment and Planning and reports to Cabinet at key milestones by agreement between the Cabinet Member for Environment and Planning and the Leader of the Council.

Reasons for Decisions:

 

To authorise development of the Eco Park, an essential part of the Waste Strategy and a priority for the council.

 

[The decisions on this item can be called in by the Environment and Transport Select Committee]