Issue - decisions

Digital Business & Insights Programme Re-Planning

21/12/2021 - Digital Business & Insights Programme Re-Planning

RESOLVED:

 

1.    That Cabinet approve the £1.25m revenue and £1.91m capital funding required for the project extension to complete go-live of the new Unit4 ERP system in April 2022.

Reasons for Decisions:

 

The recommendation to approve the funding request will enable the programme to complete the implementation of the Unit4 ERP system and deliver its benefits. This includes addressing urgent technical drivers for change, while also enabling the council to achieve its ambitions to transform services, drive efficiencies, improve management decision making and to fully enable a flexible and mobile workforce.

(This item can be called in by the Resources and Performance Select Committee]