It was AGREED that following a mini-competition tendering exercise and extensive pre-construction preparation, contracts be awarded for main construction works for the 2013/14 schools capital construction projects at Horley NE Primary School and Langshott Infants School to the contractors identified in paragraphs 2 and 3 of the Contract Award report.
It was AGREED that following a mini-competition tendering exercise and extensive pre-construction preparation, a contract be awarded for early enabling works for the 2013/14 schools capital construction project at Horley NE Primary School to the contractor identified in paragraph 3 of the Contract Award report.
It was AGREED that following a mini-competition tendering exercise and extensive pre-construction preparation, a contract be awarded for the 2013/14 schools capital construction project at Esher High School to the contractor identified in paragraph 3 of the Contract Award report.