Issue - decisions

Monthly Budget Monitoring Report

23/04/2014 - Flash Outturn Report for 2013/14 and Proposed Carry Forward Requests for 2014/15

(1)     That the provisional year end revenue budget outturn of £6.1m underspend, as set out in Table 1 and paragraphs 2 to15 of the submitted report, be noted.

 

(2)     That Services’ revenue budget carry forward requests totalling £4.9m, as set out in Table 2 of the submitted report, be approved.

 

(3)     That the provisional year end capital budget outturn £0.5m overspend, including £39.9m underspend on Services, as set out in Table 3 and paragraphs 18 to 23 of the submitted report, be approved.

 

(4)     That Services’ capital budget carry forward requests for £39.4m, as set out in Table 4 of the submitted report, be approved.

 

Reasons for Decisions:

To continue to provide monthly budget monitoring information to Cabinet and to enable Cabinet to consider services’ requests to carry forward funding for approval.

 

[The decisions on this item can be called in by the Council Overview and Scrutiny Committee]