Developing Local Special Educational Needs And Disability (SEND) Provision In Surrey To Meet Demand In 2023/24 Onwards

Bramley Oak Academy’s expansion by 49 places and change of gender from single sex to co-educational provision is one of the approved projects under Phase 4 of the SEND Capital programme. The school transferred from local authority control to London and Southeast (LSEAT) Academy Trust in late 2020. LSEAT are the leaseholder on standard DfE terms for 125 years.

As part of the transfer to Academy status, LSEAT obtained a commitment from DfE for c£3m grant to address immediate ‘condition and suitability’ issues for the 55 PAN (Pupil Admission Number) pupils at the Academy. Grant conditions from DfE are clear that these monies are not to be used in support of expansion and are specifically to address the condition and suitability issues at the Academy. Given the delays to the planned condition and suitability work because of the pandemic, it would be appropriate to combine works for both ‘condition and suitability’ (funded by DfE) with those for ‘expansion’ (funded by SCC) into one set of coordinated plans. This approach has been agreed in principle between the Academy, DfE Policy and SCC’s SEND Capital Programme.

With both condition and suitability works (funded by DfE) together with expansion (funded by SCC), a set of coordinated design layout proposals have been developed, at risk by the Trust. Works to support condition and suitability (funded by DfE) together with expansion (funded by SCC) are proposed in two distinct projects:

Project 1: Full phased refurbishment and remodelling of the existing layout for both expansion and condition/suitability works: Jointly funded by DfE and SCC, delivered by LSEAT under SCC Self-Delivery Contract

Project 2: New build expansion blocks and refurbishment/ remodelling of existing kitchen, dining, and hall spaces (once new hall and dining/kitchen constructed): Funded and delivered by SCC.

At the conclusion of all works proposals will be the ability to phase in the additional 49 places over a period of 5 years from Sep 2024-Sep 2028 to achieve a 104 PAN (Pupil Admission Number).

The Capital investment required to complete the Bramley Oak expansion is £6.95m. This is based on a £0.14m per pupil place for modernisation as well as new build expansion. The cost per pupil place varies significantly from one project to another. The reason for this is that the programme includes both new build and provision within existing assets (i.e., requiring refurbishment or remodelling) as well as several modular solutions, with a range of costs that reflect different scope of work to deliver the additional specialist school places. This new build project is at the upper end of the cost per pupil place range and includes contingency for inflation risk.

The project will realise £1.47m total cost containment to DSG HNB per year. This is based on an average unit cost of £53k per pupil per annum for independent sector provision, as compared to the average cost for maintained specialist places at £23k per learner per annum. Provision of additional maintained specialist places would generate an approximate saving from 2024-2028 of £30k per place per year.

 

A sustainable specialist education estate will be developed to provide fit for purpose facilities for Surrey’s children and young people who have SEND and require a specialist school placement, providing cost effective solutions to support revenue savings. The investment will be funded from existing capital programme budgets within Education.

 

Decision type: Key

Decision status: Recommendations Approved

Notice of proposed decision first published: 22/12/2021

Decision due: 25 Jan 2022 by Cabinet

Decision due: 5 May 2022 by Cabinet Member for Education and Learning, Cabinet Member for Property, Waste and Infrastructure, Deputy Leader and Cabinet Member for Finance and Resources

Lead member: Cabinet Member for Education and Learning

Lead director:

Contact: Emily George, Assistant Director - SEND Systems Email: emily.george@surreycc.gov.uk Tel: 07793115844.

Consultees

Maintained mainstream secondary schools

Maintained special schools

Surrey SEND Partnership Board

 

Decisions